Redevelopment of

Queen Mary Hospital, phase 1

31 Aug 2018
Relocation of Clinical Pathology Building, Pathology Building(HKU) and Housemen Quarters to Block T
22 Feb 2017
Conversion works of Senior Staff Quarters for decanting purpose.
The Senior Staff Quarters is renamed as Block T after conversion into clinical pathology laboratories, staff accommodation, teaching facilities and car parking facilities for the decanting of the existing facilities and equipment in the Clinical Pathology Building (CPB), University Pathology Building (UPB) and Housemen Quarters (HQ). The conversion commenced on 28 July 2014 and was substantially completed in March 2017 .


18 May 2018
Funding approval for the main works of phase 1 redevelopment of Queen Mary Hospital project obtained from Finance Committee of the Legislative Council.
On 18 May 2018, Finance Committee of the Legislative Council approved the funding of HK$13,556.0 million for main works of phase 1 redevelopment of Queen Mary Hospital.  It is planned to commence the main works in October 2018 for completion of the whole project in 2024. The project aims at rebuilding the hospital into a modern medical centre with additional space to meet operational needs, as well as improved physical design and accessibility for more efficient clinical operations and the promotion of integrated research and education.


31 Aug 2018
Relocation of Clinical Pathology Building, Pathology Building(HKU) and Housemen Quarters to Block T
To vacate Clinical Pathology Building, Pathology Building (HKU) and Housemen Quarters for the demolition works and construction of a new block, the final phase of the relocation works was completed in early August 2018. The facilities and services of the aforementioned three buildings (e.g. laboratories of Department of Pathology and Department of Microbiology, teaching facilities, offices of clinical departments, call rooms, etc.) have been smoothly relocated to Block T (the converted Senior Staff Quarters) and have commenced full operation.

2018
2017
22 Feb 2017
Conversion works of Senior Staff Quarters for decanting purpose.
31 Aug 2018
Relocation of Clinical Pathology Building, Pathology Building(HKU) and Housemen Quarters to Block T
18 May 2018
Funding approval for the main works of phase 1 redevelopment of Queen Mary Hospital project obtained from Finance Committee of the Legislative Council.