Redevelopment of

Queen Mary Hospital, phase 1

2024
2018
Main Works start
Oct 2018
Main works of the project commenced in October 2018.
Finance Committee of the Legislative Council
May 2018
Funding approval obtained from Finance Committee of the Legislative Council for the main works of the redevelopment of QMH, phase 1 project.
Public consultation
Mar 2018
Members of the Southern District Council supported the project in March 2018.
Block T
Aug 2018
The facilities and services of Clinical Pathology Building, Pathology Building (HKU) and Housemen Quarters have been relocated to Block T and have commenced full operation in August 2018.
Panel on Health Services of the Legislative Council
Mar 2018
Members of the Panel on Health Services of the Legislative Council supported the main works of the project in March 2018.
Public consultation
Feb 2018
Members of the Central and Western District Council supported the project in February 2018.
2017
Project Completion of the conversion works of Senior Staff Quarters
2017
Conversion works of Senior Staff Quarters was substantially completed in March 2017.
2014
Preparatory works start
Jul 2014
The preparatory works commenced in July 2014 and the conversion works of Senior Staff Quarters were kicked off.
Panel on Health Services of
the Legislative Council
Feb 2014
Members of the Panel on Health Services of the Legislative Council supported the preparatory works of the project in February 2014.
Finance Committee of
the Legislative Council
Jul 2014
Funding approval obtained from Finance Committee of the Legislative Council for the preparatory works of the redevelopment of QMH, phase 1 project.
2013
Public consultation
Nov 2013
Members of the Central and Western District Council and Southern District Council supported the project in November 2013.
Handover of Senior Staff Quarters.
Sep 2013
The SSQ was handed over from HKSAR Government to Hospital Authority on 30 September 2013 in order to facilitate the commencement of conversion works in the 2nd quarter of 2014.