Redevelopment of

Prince of Wales Hospital, phase 2 (stage 1)

24 Jun 2022
Funding approval obtained from the Finance Committee of the Legislative Council for the main works of Redevelopment of PWH, phase 2 (stage 1)
09 Mar 2017
Engaging stakeholders in the district

The Health and Environment Committee of the Sha Tin District Council was consulted on 9 March 2017.
19 Jul 2017
Funding approval obtained from the Finance Committee of the Legislative Council for the preparatory works of Redevelopment of Prince of Wales Hospital, phase 2 (stage 1).
On 19 July 2017, Finance Committee of the Legislative Council approved the funding of HK$1,231.1 million for the preparatory works of Redevelopment of Prince of Wales Hospital, phase 2 (stage 1).
10 Jan 2019
Public consultation
Members of the Health and Environment Committee of the Sha Tin District Council supported the proposed demolition and foundation works on 10 January 2019.
18 Mar 2019
Panel on Health Services of the Legislative Council
Members of the Panel on Health Services of the Legislative Council supported the demolition and foundation works on 18 Mar 2019.
22 Nov 2019
Funding approval obtained from the Finance Committee of the Legislative Council for the demolition and foundation works of Redevelopment of Prince of Wales Hospital, phase 2 (stage 1).
On 22 November 2019, Finance Committee of the Legislative Council approved the funding of HK$1,725.0 million for the demolition and foundation works of Redevelopment of Prince of Wales Hospital, phase 2 (stage 1).
18 Jan 2022
Public consultation
Members of the Development, Housing, Environment and Health Committee of the Sha Tin District Council supported the proposed main works on 18 January 2022.
01 Apr 2022
Panel on Health Services of the Legislative Council
Members of the Panel on Health Services of the Legislative Council supported the main works of Redevelopment of PWH, phase 2 (stage 1) on 1 April 2022.
24 Jun 2022
Funding approval obtained from the Finance Committee of the Legislative Council for the main works of Redevelopment of PWH, phase 2 (stage 1)
On 24 June 2022, Finance Committee of the Legislative Council approved the funding of HK$21,978.8 million for the main works of Redevelopment of PWH, phase 2 (stage 1).
2022
2019
2017
19 Jul 2017
Funding approval obtained from the Finance Committee of the Legislative Council for the preparatory works of Redevelopment of Prince of Wales Hospital, phase 2 (stage 1).
09 Mar 2017
Engaging stakeholders in the district

22 Nov 2019
Funding approval obtained from the Finance Committee of the Legislative Council for the demolition and foundation works of Redevelopment of Prince of Wales Hospital, phase 2 (stage 1).
18 Mar 2019
Panel on Health Services of the Legislative Council
10 Jan 2019
Public consultation
24 Jun 2022
Funding approval obtained from the Finance Committee of the Legislative Council for the main works of Redevelopment of PWH, phase 2 (stage 1)
01 Apr 2022
Panel on Health Services of the Legislative Council
18 Jan 2022
Public consultation