Extension of

Operating Theatre Block for Tuen Mun Hospital

01 Mar 2022
Occupation Permit for the new Operating Theatre block was obtained in Feb 2022
22 Apr 2016
Funding approval obtained from Finance Committee of the Legislative Council for the substructure and utilities diversion works of Extension of Operating Theatre Block for Tuen Mun Hospital.
On 22 April 2016, Finance Committee of the Legislative Council approved the funding of HK$167.2 million for the substructure and utilities diversion works of Extension of Operating Theatre Block for Tuen Mun Hospital.
01 May 2016
Commencement of the substructure and utilities diversion works of Extension of Operating Theatre Block for Tuen Mun Hospital.
Subsequent to the funding approval from Finance Committee of the Legislative Council, the substructure and utilities diversion works of Extension of Operating Theatre Block for Tuen Mun Hospital commenced in May 2016.


10 Jan 2017
The extension of Operating Theatre block for TMH supported by the Social Services Committee of Tuen Mun District Council.
On 10 January 2017, Hospital Authority reported the updated status of the extension of Operating Theatre Block for Tuen Mun Hospital at the meeting of the Social Services Committee of Tuen Mun District Council. Members of the Committee supported the project.
19 Jul 2017
Funding approval obtained from Finance Committee of the Legislative Council for the main works of Extension of Operating Theatre Block for Tuen Mun Hospital.
On 19 July 2017, Finance Committee of the Legislative Council approved the funding of HK$2,729.7 million for the main works of Extension of Operating Theatre Block for Tuen Mun Hospital.
01 Sep 2017
Commencement of the main works of Extension of Operating Theatre Block for Tuen Mun Hospital.
Subsequent to the funding approval from Finance Committee of the Legislative Council, the main works of Extension of Operating Theatre Block for Tuen Mun Hospital commenced in September 2017 for completion in 2022.

29 Mar 2018
Completion of the substructure and utilities diversion works of Extension of Operating Theatre Block for Tuen Mun Hospital.
The site works for substructure and utilities diversion works of Extension of Operating
Theatre Block for Tuen Mun Hospital was completed in 29 March 2018.
01 Mar 2022
Occupation Permit for the new Operating Theatre block was obtained in Feb 2022
Subsequent to the funding approval from Finance Committee of the Legislative Council, the main works of Extension of Operating Theatre Block for Tuen Mun Hospital commenced in September 2017 for completion of the construction of new OT extension block in 2022.

2022
2018
2017
2016
01 May 2016
Commencement of the substructure and utilities diversion works of Extension of Operating Theatre Block for Tuen Mun Hospital.
22 Apr 2016
Funding approval obtained from Finance Committee of the Legislative Council for the substructure and utilities diversion works of Extension of Operating Theatre Block for Tuen Mun Hospital.
01 Sep 2017
Commencement of the main works of Extension of Operating Theatre Block for Tuen Mun Hospital.
19 Jul 2017
Funding approval obtained from Finance Committee of the Legislative Council for the main works of Extension of Operating Theatre Block for Tuen Mun Hospital.
10 Jan 2017
The extension of Operating Theatre block for TMH supported by the Social Services Committee of Tuen Mun District Council.
29 Mar 2018
Completion of the substructure and utilities diversion works of Extension of Operating Theatre Block for Tuen Mun Hospital.
01 Mar 2022
Occupation Permit for the new Operating Theatre block was obtained in Feb 2022