Extension of

Operating Theatre Block for Tuen Mun Hospital

Project completion
The new OT extension block was completed in 2022 while the remaining works and alteration and addition works are in progress.
Banner
2022
2018
Completion of substructure and utilities diversion works
Mar 2018
Substructure and utilities diversion works were completed in March 2018.
2017
Main works start
Sep 2017
Main works commenced in September 2017.
Panel on Health Services of the Legislative Council
Apr 2017
Members of the Panel on Health Services of the Legislative Council supported the main works of the project in April 2017.
Finance Committee of the Legislative Council
Jul 2017
Funding approval for the main works was obtained from Finance Committee of the Legislative Council.
Public consultation
Jan 2017
Hospital Authority reported the project’s updated progress to the SSC of the TMDC in January 2017. Members of the SSC of the TMDC supported the extension project.
2016
Commencement of substructure and utilities diversion works start
May 2016
Substructure and utilities diversion works commenced in May 2016.
Finance Committee of the Legislative Council
Apr 2016
Funding approval obtained from Finance Committee of the Legislative Council for the substructure and utilities diversion works.
2015
Panel on Health Services of the Legislative Council
May 2015
Members of the Panel on Health Services of the Legislative Council supported the extension project in May 2015.
Public consultation
May 2015
Members of the Social Services Committee (SSC) of the Tuen Mun District Council (TMDC) supported the extension of OT block of TMH in May 2015.