New Acute Hospital at Kai Tak Development Area

Project completion
Project anticipated to be completed in 2024.
2024
2018
Foundation works started
Sep 2018
The foundation, excavation and lateral support, and basement excavation commenced in September 2018.
Panel on Health Services of the Legislative Council
Mar 2018
Members of the Panel on Health Services of the Legislative Council supported the foundation, excavation and lateral support, and basement excavation works in March 2018.
Finance Committee of the Legislative Council
May 2018
Funding approval obtained from Finance Committee of the Legislative Council for the foundation, excavation and lateral support, and basement excavation of New Acute Hospital at Kai Tak Development Area.
Public consultation
Jan 2018, Jan 2018, Feb 2018
Members of the Kwun Tong District Council, Kowloon City District Council, Wong Tai Sin District Council and Yau Tsim Mong District Council supported the project in January 2018 and February 2018 respectively.
2017
Preparatory works started
Sep 2017
The preparatory works commenced in September 2017.
Panel on Health Services of the Legislative Council
May 2017
Members of the Panel on Health Services of the Legislative Council supported the project in May 2017.
Finance Committee of the Legislative Council
Jul 2017
Funding approval obtained from Finance Committee of the Legislative Council for the preparatory works of New Acute Hospital at Kai Tak Development Area.
2016
Public consultation
Nov 2016
Members of the Kwun Tong District Council, Kowloon City District Council, Wong Tai Sin District Council and Yau Tsim Mong District Council supported the project in November 2016, December 2016, January 2017 and March 2017 respectively.